Blind Flange

Blind flanges—attached by a mechanical bolt up to any mating flange.

From: The Fundamentals of Piping Design, 2007

Add to Mendeley

Flange Basics

Roy A. Parisher, Robert A. Rhea, in Pipe Drafting and Design (Fourth Edition), 2022

Blind Flange

The blind flange depicted in Figure 4.24 serves a function similar to that of a plug or cap. It is used to terminate the end of a piping system. The blind flange is basically a flange that does not have a hub or a bored center. Blind flanges have the face thickness of a flange, a matching face type, and similar bolting pattern. Blind flanges can also be used to seal a nozzle opening on a pressure vessel. Because it is bolted, the blind flange provides easy access to the interior of a vessel or pipe, unlike a cap that is welded. Figure 4.25 represents the drawing symbol for the blind flange.

Figure 4.24. Blind flange.

Figure 4.25. Blind flange drawing symbols.

Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780128220474000054

Transportation Pipelines Pressure Testing

Alireza Bahadori PhD, CEng, MIChemE, CPEng, MIEAust, RPEQ, in Oil and Gas Pipelines and Piping Systems, 2017

4.4 Test Preparation

All sections to be tested should be isolated by blind flanges, weld caps, or blanking plates with a design pressure exceeding the maximum test pressure.

Testing should be carried out only when the engineer or his authorized representative is present to witness the test.

Provisions should be made for filling, bleeding, and complete drainage of the test water from each test section. Drain points should be at the lowest points and bleed-off points should be at the highest points in each test section, if practical.

Prior to commencement of the test, a thorough check should be made to ensure all fittings, caps, flanges, etc., are in place. All flanges and flanged fittings should be bolted and bolts should be properly torqued.

The executor should obtain sufficient and satisfactory water to hydrostatically test the pipeline. Bore water should not be used, except as approved by the engineer for cases in which surface water is not practically available.

The executor should pump, filter, and measure the fill water required for hydrostatic testing.

The executor should, at his own expense, carry out the water analysis at each water supply point and hand over the analysis results to the engineer. The executor should treat the water, if necessary, at each water supply point with chemicals as directed by the engineer.

The executor should supply all chemicals necessary for water treatment at his cost.

Before water is taken by the executor from any source for testing, the company will obtain the necessary permission or grants from the requisite authorities, public or private. The executor should submit request for the permission 1 month in advance of the test date.

Water should be filtered before entering the pipeline with a filter arrangement in which the filter can be cleaned without disconnecting the piping. The filter should be capable of removing 99% of all particles that are 140 µm or more in diameter.

Measuring equipment for pressure and temperature should be supplied complete with their calibration certificate from a laboratory acceptable to the engineer.

The executor should ensure that all piping components and accessories within the test section are correctly positioned, that all end caps on the test section including those on off-takes are adequately braced to withstand any movement, and that elbows within the test section are adequately padded or otherwise supported to prevent movement.

Before commencement of test on any section, the executor should give the engineer a written notice at least 1 week in advance of the test date. Any changes to the test date should be relayed to the engineer as soon as such changes are known.

Check valves used in liquid petroleum pipeline should be a full-opening, swing type to permit running pigs.

Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780128037775000046

General Design

DENNIS R. MOSS, in Pressure Vessel Design Manual (Third Edition), 2004

Notes

1.

For flat heads, tubesheets, and blind flanges, the thickness used for each of the respective thickness' is that thickness divided by 4.

2.

For corner, fillet, or lap-welded joints, the thickness used shall be the thinner of the two parts being joined.

3.

For butt joints, the thickness used shall be the thickest joint.

4.

For any Code construction, if the vessel is stress relieved and that stress relieving was not a Code requirement, the MDMT for that vessel may be reduced by 30 ° without impact testing.

General Notes on Assignment of Materials to Curves (Reprinted with permission from ASME Code, Section VIII, Div. 1.)

a.

Curve A-all carbon and all low alloy steel plates, structural shapes, and bars not listed in Curves B, C, and D below.

b.

Curve B

1.

SA-285 Grades A and B

SA-414 Grade A

SA-515 Grades 55 and 60

SA-516 Grades 65 and 70 if not normalized

SA-612 if not normalized

SA-662 Grade B if not normalized

2.

all materials of Curve A if produced to fine grain practice and normalized which are not listed for Curves C and D below.

3.

except for bolting (see (e) below), plates, structural shapes, and bars, all other product forms (such as pipe, fittings, forgings, castings, and tubing) not listed for Curves C and D below.

4.

parts permitted under UG-11 shall be included in Curve B even when fabricated from plate that otherwise would be assigned to a different curve.

c.

Curve C

1.

SA-182 Grades 21 and 22 if normalized and tempered

SA-302 Grades C and D

SA-336 Grades F21 and F22 if normalized and tempered

SA-387 Grades 21 and 22 if normalized and tempered

SA-516 Grades 55 and 60 if not normalized

SA-533 Grades B and C

SA-662 Grade A

2.

all material of Curve B if produced to fine grain practice and normalized and not listed for Curve D below.

d.

Curve D

SA-203

SA-508 Class 1

SA-516 if normalized

SA-524 Classes 1 and 2

SA-537 Classes 1 and 2

SA-612 if normalized

SA-622 if normalized

e.

For bolting the following impact test exemption temperature shall apply:

Spec. No. Grade Impact Test Exemption Temperature, °F
SA-193 B5 −20
SA-193 B7 −40
SA-193 B7M −50
SA-193 B16 −20
SA-307 B −20
SA-320 B L7, L7A, L7M, L43 Impact tested
SA-325 1, 2 −20
SA-354 BC 0
SA-354 BD +20
SA-449 −20
SA-540 B23/24 + 10
f.

When no class or grade is shown, all classes or grades are included.

g.

The following shall apply to all material assignment notes:

1.

Cooling rates faster than those obtained by cooling in air, followed by tempering, as permitted by the material specification, are considered to be equivalent to normalizing or normalizing and tempering heat treatments.

2.

Fine grain practice is defined as the procedures necessary to obtain a fine austenitic grain size as described in SA-20.

Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780750677400500020

General Design

Dennis R. Moss, Michael Basic, in Pressure Vessel Design Manual (Fourth Edition), 2013

Notes

1.

For flat heads, tubesheets, and blind flanges, the thickness used for each of the respective thickness’ is that thickness divided by 4.

2.

For corner, fillet, or lap-welded joints, the thickness used shall be the thinner of the two parts being joined.

3.

For butt joints, the thickness used shall be the thickest joint.

4.

For any Code construction, if the vessel is stress relieved and that stress relieving was not a Code requirement, the MDMT for that vessel may be reduced by 30° without impact testing.

Design Conditions (for example)

D.T. = 700°F

P = 400 PSIG

C.a. = 0.125

Ri = 30 in

E (Shell) = 0.85

E (Head) = 1.00

MDMT for vessel = + 11°F

General Notes on Assignment of Materials to Curves (Reprinted with permission from ASME Code, Section VIII, Div. 1.)

a.

Curve A—all carbon and all low alloy steel plates, structural shapes, and bars not listed in Curves B, C, and D below.

b.

Curve B

Figure 2-41. Dimensions of vessel used for MDMT example.

1.

SA-285 Grades A and B

SA-414 Grade A

SA-515 Grade 60

SA-516 Grades 65 and 70 if not normalized

SA-612 if not normalized

SA-662 Grade B if not normalized

2.

all materials of Curve A if produced to fine grain practice and normalized which are not listed for Curves C and D below.

3.

except for bolting (see (e) below), plates, structural shapes, and bars, all other product forms (such as pipe, fittings, forgings, castings, and tubing) not listed for Curves C and D below.

4.

parts permitted under UG-11 shall be included in Curve B even when fabricated from plate that otherwise would be assigned to a different curve.

c.

Curve C

1.

SA-182 Grades F21 and F22 if normalized and tempered

SA-302 Grades C and D

SA-336 Grades F21 and F22 if normalized and tempered

SA-387 Grades 21 and 22 if normalized and tempered

SA-516 Grades 55 and 60 if not normalized

SA-533 Grades B and C

SA-662 Grade A

2.

all materials of Curve B if produced to fine grain practice and normalized and not listed for Curve D below.

d.

Curve D

SA-203

SA-508 Class 1

SA-516 if normalized

SA-524 Classes 1 and 2

SA-537 Classes 1, 2, and 3

SA-612 if normalized

SA-622 if normalized

e.

For bolting the following impact test exemption temperature shall apply:

Spec. No. Grade Impact Test Exemption Temperature, °F
SA-193 B5 –20
SA-193 B7 –40
SA-193 B7M –55
SA-193 B16 –20
SA-307 B –20
SA-320 B L7, L7A, L7M, L43 Impact tested
SA-325 1, 2 –20
SA-354 BC 0
SA-354 BD +20
SA-449 –20
SA-540 B23/24 +10
f.

When no class or grade is shown, all classes or grades are included.

g.

The following shall apply to all material assignment notes:

1.

Cooling rates faster than those obtained by cooling in air, followed by tempering, as permitted by the material specification, are considered to be equivalent to normalizing or normalizing and tempering heat treatments.

2.

Fine grain practice is defined as the procedures necessary to obtain a fine austenitic grain size as described in SA-20.

Figure 2-44. Flow chart showing decision-making process to determine MDMT and impact-testing requirements.

Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780123870001000024

Thermal Expansion Design

Qiang Bai, Yong Bai, in Subsea Pipeline Design, Analysis, and Installation, 2014

Unrestrained Pipeline

Figure 9.5 shows a constant cross section of unrestrained pipeline fitted with blind flanges at the end under constant internal pressure, pi; external pressure, pe; and constant temperature, T, along the pipeline. The restraint force, Fext, in the blind flange (capped end) is a function of wall force and fluid force, as expressed in Eq. [9.14]:

Figure 9.5. Unrestrained pipeline with constant pressure and temperature.

[9.21]Fext=FwFf

The fluid force is due to the fluid pressure acting on the end caps and can be expressed as follows:

Ff=piAipeAe

The restraint force (anchor force) is zero for unrestrained pipeline:

Fext=0

The wall force at the capped end is due to the internal and external pressures:

Fw=piAipeAe

When an unrestrained pipeline expands due to a temperature increase, there is a strain change due to the temperature effect but with no stress change due to the temperature effect. The wall force along the pipeline is constant because no restraint force is acting along the pipe and the longitudinal stress of unrestrained pipeline is

[9.22]σl,U=piAipeAeAs

The hoop stress and radial stress are calculated from Eq. [9.12].

The end expansion movement at the free end is

[9.23]Δ=(εP+εT)L
Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780123868886000092

Thermal Insulation Installations

Alireza Bahadori PhD, in Thermal Insulation Handbook for the Oil, Gas, and Petrochemical Industries, 2014

2.5 Hot Insulation

Vessel manways, handholes, weep hole nipples, sample connections, nozzles with blind flanges, exchanger tube sheets, flanges, etc. shall not be insulated on hot insulated vessel exchangers or equipment, but shall be insulated where required for acoustical control. If they are to be insulated, preformed insulation of a design permitting removal and replacement shall be applied.

Piping bends are usually insulated to the same specifications as the adjacent straight piping. Where preformed material is used it shall be cut in mitered-segment fashion and wired or strapped into position; alternatively, prefabricated or fully molded half-bends may be used if these are available. Plastic composition may be used to seal any gaps that may appear between mitered segments.

It is preferable that flanges, valves, and other fittings on hot piping above 300°C be insulated, but where hidden flange leakage may cause a possible fire or other hazard, e.g., with oil lines, or where repeated access will make it uneconomical, insulation may be omitted.

Valves and flanges in piping for viscous fluids, e.g., asphalt and paraffin wax service, and in all lines in services above 300°C shall be provided with removable insulation covers. Attention shall be paid to the insulation details to prevent leaking product into the line insulation. Drainage outlets should be provided to give visible indication of a possible valve or flange leak.

Bonnet and channel hangs on heat exchangers shall preferably be insulated by means of a removable double skin box. If the weight of the box exceeds 25 kg it shall be in two or more parts and the weight of each part be less than 25 kg.

For heat exchangers on hydrogen duty, tube-sheet and channel flanges shall not be insulated, but a simple removable galvanized sheet metal protecting shroud shall be placed over the bolts to protect them from the effect of thermal shock from rain storms. A suitable gap shall be left between the bolts and the shroud to allow adequate ventilation. Also flanges for hydrogen service shall never be insulated.

Steam traps and the outlet side of the steam trap piping shall not be insulated. Lines to steam traps shall be insulated. In the case of thermostatic type traps, 600 mm to 1000 mm of line before trap shall be left uninsulated.

Heat exchanger flanges, exchanger channels and shell covers, saddle support for horizontal equipment, equipment shell closure flanges, nozzles to which noninsulated piping is attached, tube unions, and tube and shell connectors on fin-tube exchangers also shall not be insulated unless specified otherwise or required for personnel protection.

The bodies of safety valves shall not be insulated. Steam condensate lines shall remain uninsulated except as required for personnel or freeze protection.

Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780128000106000022

Corrosion Atlas

In Corrosion Atlas Case Studies, 2022

Contributed By: Isabel Díaz-Tang

Case History 02.21.11.001

Type of Material Stainless steel AISI 304 L
System Double-pass reverse osmosis equipment
Name of the Part Blind flange
Phenomenon Crevice corrosion (differential aeration cells)

The hands serve as a reference. Crevice corrosion on a flange, showing reddish-brown corrosion products, with (left) and without (right) gasket.
Appearance Localized attack (pits and reddish-brown corrosion products) along the edge of the gasket.
Time in Service One year
Environment Concentrate in carbonated beverage production (information about the chemical composition was not available).
Causes Poor sealing of the gasket on the flange. Formation of differential aeration cells, concentrate constitutes an electrolytic medium.
Remedy Provide adequate sealing of the gasket on the flange
Additional References Pertaining to Case Study
Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780323858496000020

Engineering Aspects for Plant Piping Systems

Alireza Bahadori PhD, CEng, MIChemE, CPEng, MIEAust, RPEQ, in Oil and Gas Pipelines and Piping Systems, 2017

13.2.11.1.1 Positive Isolation

1.

Positive isolation should be by one of the following:

a.

The removal of a flanged spool piece or valve and the fitting of blind flanges to the open-ended pipes.

b.

Line blind.

c.

A spade in accordance with standards. The arrangements of spading points, together with venting, draining, and purging facilities, should enable a section of line containing a spade to be checked as free from pressure before spade insertion or removal.

2.

Positive isolation methods should be provided:

a.

To permit isolation of major items of equipment or group of items for testing, gas freeing, making safe, etc. A group of items containing no block valves in the interconnecting pipework may be considered as one item of equipment.

b.

To isolate a section of plant for overhaul.

c.

To isolate utility services, e.g., fuel gas, fuel oil, atomizing, snuffing, or purge steam to individual fired heaters.

d.

To prevent contamination of utility supplies, e.g., steam, water, air, and nitrogen where permanently connected to a process unit.

e.

Steam and air connections for regeneration and steam/air decoking should be positively isolated from the steam and air systems, preferably by spool pieces or swing bends.

Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780128037775000137

Regulation of Chemical Process Safety

Daryl Attwood, in Methods in Chemical Process Safety, 2017

7.1 Piper Alpha: Offshore Oil and Gas Production Platform Explosion and Fire in the UK North Sea, 1988

The Piper Alpha platform exploded and burned in the North Sea on July 6, 1988 (Wikipedia, Piper Alpha, 2016), resulting in the deaths of 167 personnel and causing property damage of £1.7 billion. The platform, originally designed and constructed for oil only operation but subsequently modified to add gas production, accounted for about 10% of North Sea production. At the time, the accident was the worst ever offshore oil disaster, both in terms of lost lives and property damage.

The direct cause of the accident was overpressure in one of the two parallel condensate pumps, which could not be withstood by an improperly fitted temporary blind flange. The first pump, originally called upon, failed. The second, subsequently called upon, had its pressure safety valve removed and replaced by the loosely fitted blind flange by an earlier shift as part of partially completed routine maintenance. Gas then leaked out of the pump/flange and was ignited, causing an explosion which blew through a firewall designed to withstand fire, but not explosions. Some other issues associated with the accident were as follows, together with suggestions of how a rigorous regulatory program might have averted the disaster.

Ineffective PTW process. A PTW covering the status of the pump undergoing maintenance was in place. It was generated by day shift personnel and stated that the pump was not ready and should not be switched on under any circumstances. Unfortunately, the situation was not discussed directly with the incoming night shift foreman. Instead, the permit, which could not subsequently be found, was simply left in the control center.

PTW systems and procedures are key elements of safety cases and are also mandated by other regulatory requirements. PTW procedures are usually required to be part of the formal documentation submitted for review and approval to the regulator, classification society, and/or CA. Procedures generally require sign-off at all stages of the work, including handover from one group or shift to the next. The argument could be made that had the night shift foreman been required to formally sign-off all active work permits in place during his upcoming shift, the disaster may have been averted.

Communication is also a key element of the safety case process. Usually a communications plan is required, which would include, for example, short tool-box style meetings between personnel ending and beginning their shifts. It is quite possible that had such a meeting taken place, the condition of the pump undergoing maintenance would have been known to the night shift staff.

Unacceptable design. A contributory factor in the disaster was the inability of the firewall to withstand an explosion. In fact one panel from the firewall was violently dislodged and caused a rupture in another pipe and subsequently another fire. Design review and approval of all safety-related structures and equipment are primary elements of all regulatory programs, both prescriptive and those relying on safety cases. It is quite likely that the unsuitability of the firewall for the facility's current configuration would have been picked up by the design appraisal process.

Notification of changes to the facility. Regulatory programs require operators to advise the regulator, classification society, and/or CA when any significant changes are made to the facility. The Piper Alpha platform was originally intended to produce oil only, but was reconfigured to add gas production. This would certainly constitute a significant change.

One of the significant changes associated with this would have been the upgrade of the firewall to a blast wall. Had there been a rigorous process in place to review all aspects of the changes it is quite possible that the effect of this contributory factor could have been minimized or eliminated altogether.

A second and more fundamental result of the change from oil only to oil and gas production was the breaking of the basic safety concept that the most dangerous operations should be kept as far away as possible from personnel areas. The change resulted, for example, in gas compression equipment being located next to the control room. This change was also considered to be a contributory factor in the disaster.

Ineffective interfield communications and levels of authority. The fire would have burned out more quickly except that oil from two adjacent platforms, Tartan and Claymore, continued to feed it. The managers of the adjacent platforms either believed they had no authority to stop production, or they were directly instructed by their superiors to continue production.

Regulatory programs and safety cases have requirements for clearly defined, submitted, and approved communications plans, level of authority matrices and similar. It is quite likely that such plans would provide for communications protocols in emergency situations and give offshore installations managers the complete authority to take any appropriate steps they considered necessary to safeguard life and property in the event of an incident. This would have been an obvious mitigative step in dealing with the disaster.

Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/S246865141730003X

High Pressure Vessels

Dennis R. Moss, Michael Basic, in Pressure Vessel Design Manual (Fourth Edition), 2013

3.3 Bolted Flat Covers

Flat, unstayed covers may be integral or loose. If they are welded in place the construction is considered as integral. These are commonly referred to as flat heads. Conversely, bolted type heads are basically blind flanges.

Flat heads may be circular or non-circular. This section does not cover non-circular heads because this would be a very rare application for a high pressure vessel. The ASME Code, Section VIII, Division 2 has formulas to follow for fixed, non-circular, flat heads.

Heads may also be what is known as an end plug such as is used in Bridgman closures and threaded closures. The end plug is peculiar to these designs and the design of these is handled in their respective sections.

The thickness of flat, bolted heads is governed by bending, and not by tension. Thus, the formulas for the design of these components is the same for Division 1 or Division 2.

For high pressure vessels, the nozzles are typically located in the end closures, and not in the shells. Frequently they have centrally located openings with either integral or non-integral (loose) attachments for nozzles. This procedure provides for the design of both types of construction.

If the centrally located opening exceeds ½ the inside diameter of the vessel, then the design procedure reverts to a standard flange design.

Read full chapter
URL: https://www.sciencedirect.com/science/article/pii/B9780123870001000085